Description
PlovdivSvilengradRailway_ProjectSection.pdf (~ 130KB)
Technical Parameters
-
Project Length – approx. 150 Km
-
Approx. 20 Km Double Track
-
Maximum Speed - 160 km/hr for conventional trains and 200 km/hr for tilting trains
-
Standard UIC Gauge – 1435 mm
-
Rails – UIC 60
-
Sections implemented for future doubling
-
‘Classic’ Single Phase 25 Kv AC 50 Hz OHL
-
27 Stations & Halts – New Build / Rehabilitation
-
Connection to 110 Kv National Power Supply – 8 Overhead Lines
-
Traction Power sub-stations 110/25 kV – 4 nr.
-
Extensive Structures – Bridges, Underpasses, Culverts Etc.
-
Signaling System (ETCS Level 1) – 252 km
-
Telecommunications – 252 km
For the purposes of the project implementation, the following contracts have been signed:
- 14.06.2005 Design and Build Contract for Civil, Track and Electrification Works for Phase 1: Krumovo - Parvomai
- 22.08.2005 Technical Assistance to the Project management and Implementation Unit within NRIC for complex project management
- 25.04.2006 Technical Assistance for the Supervision of the Whole Line
- 05.09.2007 Design and Build Contract for Civil, Track and Electrification Works for Phase 2: Parvomai – Svilengrad – Turkish / Greek Borders
- 05.09.2007 Signalling, Telecommunication and SCADA Systems for the Whole Line
- 25.05.2009 Design and Build Contract for Civil, Track and Electrification Works for Phase 3: Svilebgrad - Turkish border between NRIC and OHL ZS s.a.
WORKS CONTRACTS SUMMARY
| |
Phase1 |
Phase2 |
Phase3 |
Systems |
| Contractor |
 |
 |
 |
 |
| Base Country |
Greece |
Italy |
Czech Republic |
Austria Romania |
| Contract Value |
99,792,441 Eur |
68,000,000 Eur |
69,999,666.00 Leva |
35,557,047 Eur |
| Commerncement |
25 May 2006 |
2 October 2007 |
1 July 2009 |
16 October 2007 |
| Duration |
67 Months |
49 Months |
36 Months |
54 Months |
| Completion |
31 December 2011 |
9 November 2011 |
3 July 2012 |
31 March 2012 |
| Project Length |
37,7 Km |
29,26 Km |
17 Km |
- |
SUPERVISION CONTRACT SUMMARY
Consortium of 5 Partners
- TYPSA (Lead)
|
 |
- SYSTRA
|
 |
- Louis Berger
|
 |
- Trademco
|
 |
- Rubicon Engineering
|
 |
Contract Value – Eur 18,866,025
Contract Duration - 110 Months (to mid 1015)
SUMMARY OF THE LONG-TERM TECHNICAL ASSISTANCE CONTRACT
Consortium between two partners
- ADO S.A.
|
 |
- WSP International Sweden
|
 |
Contract Value – Eur 2,594,590
Contract Duration - 102 Months
OrIGINAL PROJECT FUNDING DISTRIBUTION FOR PHASE 1, PHASE 2 & SYSTEMS
PROJECT FUNDING DISTRIBUTION FOR PHASE 3
cOHESION FUND - 23.84 M Eur
nATIONAL cO-FINACING - 5.96 m eur