Home

Description

PlovdivSvilengradRailway_ProjectSection.pdf (~ 130KB)

Technical Parameters

  • Project Length – approx. 150 Km
  • Approx. 20 Km Double Track
  • Maximum Speed - 160 km/hr for conventional trains and 200 km/hr for tilting trains
  • Standard UIC Gauge – 1435 mm
  • Rails – UIC 60
  • Sections implemented for future doubling
  • ‘Classic’ Single Phase 25 Kv AC 50 Hz OHL
  • 27 Stations & Halts – New Build / Rehabilitation
  • Connection to 110 Kv National Power Supply – 8 Overhead Lines
  • Traction Power sub-stations 110/25 kV – 4 nr. 
  • Extensive Structures – Bridges, Underpasses, Culverts Etc.
  • Signaling System (ETCS Level 1) – 252 km
  • Telecommunications – 252 km  

For the purposes of the project implementation, the following contracts have been signed:

  • 14.06.2005 Design and Build Contract for Civil, Track and Electrification Works for Phase 1: Krumovo - Parvomai   
  • 22.08.2005 Technical Assistance to the Project management and Implementation Unit within NRIC for complex project management
  • 25.04.2006 Technical Assistance for the Supervision of the Whole Line
  • 05.09.2007 Design and Build Contract for Civil, Track and Electrification Works for Phase 2: Parvomai – Svilengrad – Turkish / Greek Borders
  • 05.09.2007 Signalling, Telecommunication and SCADA Systems for the Whole Line
  • 25.05.2009 Design and Build Contract for Civil, Track and Electrification Works for Phase 3: Svilebgrad - Turkish border between NRIC and OHL ZS s.a.

WORKS CONTRACTS SUMMARY

   Phase1  Phase2  Phase3 Systems 
 Contractor  TERNA  ASTALDI    THALES   ALCATEL
 Base Country  Greece Greece  Italy Italy  Czech Republic  Austria Austria           Roumania Rumania
 Contract Value 88,728,832 Eur 162,537,388 Eur 69,999,666.00 Leva 35,557,047 Eur 
 Commerncement 25 May 2006 2 October 2007 1 July 2009 16 October 2007
 Duration 55 Months 39 Months 24 Months 37 Months
 Completion 26 December 2010 January 2011 1 July 2011 November 2010
 Project Length 37,7 Km 104 Km 17 Km  -

 

SUPERVISION CONTRACT SUMMARY

Consortium of 5 Partners

  •  TYPSA (Lead)
  •  Spain
  •  SYSTRA
  •  France
  •  Louis Berger
  •  France
  •  Trademco
  •  Greece
  •  Rubicon Engineering
  •  Bulgaria
Contract Value – Eur 12,557,371
Contract Duration - 74 Months (to mid 1012)

 

SUMMARY OF THE LONG-TERM TECHNICAL ASSISTANCE CONTRACT

Consortium between two partners

  •  ADO S.A.
  •  Greece
  •  WSP International Sweden
  •  Sweden

Contract Value – Eur 1,819,700
Contract Duration - 60 Months

 

PROJECT FUNDING DISTRIBUTION FOR PHASE 1, PHASE 2 & SYSTEMS

 

PROJECT FUNDING DISTRIBUTION FOR PHASE 3

 

employer

beneficiary

Engineering Supervisor

Phase 1 Contractor

Phase 2 Contractor

Systems Contractor

Phase 3 Contractor

long-term technical assistance

© 2008 Plovdiv-Svilengrad Railway Supervision Team.
Made by Webfactory Bulgaria