Home

Description

PlovdivSvilengradRailway_ProjectSection.pdf (~ 130KB)

Technical Parameters

  • Project Length – approx. 150 Km
  • Approx. 20 Km Double Track
  • Maximum Speed - 160 km/hr for conventional trains and 200 km/hr for tilting trains
  • Standard UIC Gauge – 1435 mm
  • Rails – UIC 60
  • Sections implemented for future doubling
  • ‘Classic’ Single Phase 25 Kv AC 50 Hz OHL
  • 27 Stations & Halts – New Build / Rehabilitation
  • Connection to 110 Kv National Power Supply – 8 Overhead Lines
  • Traction Power sub-stations 110/25 kV – 4 nr. 
  • Extensive Structures – Bridges, Underpasses, Culverts Etc.
  • Signaling System (ETCS Level 1) – 252 km
  • Telecommunications – 252 km  

For the purposes of the project implementation, the following contracts have been signed:

  • 14.06.2005 Design and Build Contract for Civil, Track and Electrification Works for Phase 1: Krumovo - Parvomai   
  • 22.08.2005 Technical Assistance to the Project management and Implementation Unit within NRIC for complex project management
  • 25.04.2006 Technical Assistance for the Supervision of the Whole Line
  • 05.09.2007 Design and Build Contract for Civil, Track and Electrification Works for Phase 2: Parvomai – Svilengrad – Turkish / Greek Borders
  • 05.09.2007 Signalling, Telecommunication and SCADA Systems for the Whole Line
  • 25.05.2009 Design and Build Contract for Civil, Track and Electrification Works for Phase 3: Svilebgrad - Turkish border between NRIC and OHL ZS s.a.

WORKS CONTRACTS SUMMARY

   Phase1  Phase2  Phase3 Systems 
 Contractor  TERNA  ASTALDI    THALES   ALCATEL
 Base Country  Greece Greece  Italy Italy  Czech Republic  Austria Austria           Roumania Romania
 Contract Value 99,792,441 Eur 68,000,000 Eur 69,999,666.00 Leva 35,557,047 Eur 
 Commerncement 25 May 2006 2 October 2007 1 July 2009 16 October 2007
 Duration 67 Months 49 Months 36 Months 54 Months
 Completion 31 December 2011 9 November 2011 3 July 2012 31 March 2012
 Project Length 37,7 Km 29,26 Km 17 Km  -

 

SUPERVISION CONTRACT SUMMARY

Consortium of 5 Partners

  •  TYPSA (Lead)
  •  Spain
  •  SYSTRA
  •  France
  •  Louis Berger
  •  France
  •  Trademco
  •  Greece
  •  Rubicon Engineering
  •  Bulgaria
Contract Value – Eur 18,866,025
Contract Duration - 110 Months (to mid 1015)

 

SUMMARY OF THE LONG-TERM TECHNICAL ASSISTANCE CONTRACT

Consortium between two partners

  •  ADO S.A.
  •  Greece
  •  WSP International Sweden
  •  Sweden

Contract Value – Eur 2,594,590
Contract Duration - 102 Months

 

OrIGINAL PROJECT FUNDING DISTRIBUTION FOR PHASE 1, PHASE 2 & SYSTEMS

 

PROJECT FUNDING DISTRIBUTION FOR PHASE 3

cOHESION FUND - 23.84 M Eur

nATIONAL cO-FINACING - 5.96 m eur

 

employer

beneficiary

Engineering Supervisor

Phase 1 Contractor

Phase 2 Contractor

Systems Contractor

Phase 3 Contractor

long-term technical assistance

© 2008 Plovdiv-Svilengrad Railway Supervision Team.
Made by Webfactory Bulgaria